Garage Construction
Quick Facts
Helpful Information for
the Construction of a Garage
1. Fill out application for permit
(available at Building Dept., Village Hall, or on-line)
2. A Plat of Survey of your property
is to be submitted, indicating where the garage will be located.
(IF ON SEPTIC, you will need a Lake County Property Alteration
prior to issuance of a Building Permit)
3. Setback is 3 feet off side
and rear property lines, from eave of garage, except that there
must be an 18-foot setback for vehicle entrance.
4. No structure is permitted
in any easement.
5. Two detailed drawings of the
proposed construction are required.
6. The Plat of Survey must show
the location of the gas line, a garage slab may not be poured
over the gas line.
7. A detached garage must be
at least 10 feet from the main building (house)
8. Maximum height is 18 feet
from slab to ridge.
9. Electric power to the garage
must be installed underground, unless prior approval is given
by Electrical Inspector.
10. Fees:
- Permit fee is 2% of construction
cost, minimum $ 50.00
- Certificate of Compliance and
Occupancy fee of $ 25.00
- Plan Review fee of $ 25.00
|